Computer Network, City electricity, Emergency Electricity and Telephone Upgrade in Governmental Company

  • Project Manager

    Amir Ashrafi

  • Implementation Date

    1392

  • Number Of Staff

    14

  • Number Of Nodes

    770

  • Cabling Length

    38 KM

Description

The project of upgrading computer networks, city electricity, emergency electricity and telephone of Nooshahr port was launched in May 2013. The old computer network in the old office buildings, port affairs, guard and customs was collected and the new one replaced. Also, 5 earth wells with resistance below 2 ohms were created and connected to the electrical network of buildings.